October 8, 2026
The Medina Municipal/Regional Planning Commission meets at 5:30 p.m. on Monday, October 5. Two items are listed under new business, and neither one is about a house. Kevin Clark, on behalf of KOKA Development, is asking the commission to release the maintenance bonds on Graves Crossing Phase 2, Sections 1 and 2, and on Providence Subdivision Phase 1, Section 1. In a report dated September 28, the staff planner, Donny Bunton, leaves the recommendation on both items to the City Engineer.
Those bonds are money the city holds to guarantee the streets and drainage the homeowners in those sections already drive over. Every new subdivision phase in Medina goes through this same process, and it runs on its own schedule, separate from any home's closing date. If you're buying a new build here, your house closes once. The street in front of it gets finished, inspected, accepted and released in stages.
Medina's subdivision regulations were adopted in 2000 and last updated June 13, 2017. They set the same order for every phase:
The regulations define "improvements" broadly. The list includes street pavement, curbs and gutters, sidewalks and walkways, water mains, sanitary and storm sewers, drainage, erosion control, signs and landscaping. In recent staff reports, the performance bond's job is described more narrowly: making sure the street and its drainage are finished properly.
The detail that matters for buyers is when the 12-month window starts. It begins when the city accepts the improvements, not when you close. Say you buy a finished house in a phase the city hasn't accepted yet. The developer's money is still behind the street work, and the full warranty period is still ahead. Now say you buy the last lot in a phase whose maintenance bond was released a year ago. That street no longer has any developer bond behind it.
The 2026 meeting records show phases at every one of those stages, sometimes within the same family of subdivisions.
Crosswynd Section 2B sits at stage one. On April 6, 2026, the commission approved its final plat 5–1, with a $43,324 performance bond. The section creates 14 lots on 7.17 acres zoned R-1A. It extends one street, along with the water and sewer lines that go with it. The revised schematic plat for the whole subdivision was approved June 13, 2022, and the construction drawings on March 13, 2023. Crosswynd has been coming online one section at a time for years, so a house in 2B and a house in an earlier section can be at different stages even on neighboring streets.
Steeplechase Section 4 reached the same stage a month later. On May 4, 2026, the commission approved its final plat 6–0 with a $32,345 performance bond.
Graves Crossing North Phase 5 moved to stage three on June 1, 2026. The commission voted 6–0 to release its performance bond and set up a maintenance bond. Graves Crossing North will keep moving in phases for a long time. KOKA submitted a preliminary plat for 238 lots in the 1st Addition, and the commission made approval conditional on an HOA and bylaws. In August 2025, the commission approved construction drawings for Phase 6, which would create 22 more lots.
Graves Crossing Phase 2 and Providence Phase 1, Section 1 are at stage four. Both release requests are on the agenda, but neither has been approved. As of October 4 they are still requests waiting on the City Engineer's input.
A maintenance bond is set at 10% of total construction costs, so you can work backward from it to a rough size for the job it covers.
| Phase | Maintenance bond | Date set | Implied construction cost at 10% |
|---|---|---|---|
| Graves Crossing Phase 2, Section 1 | $19,647 | June 2, 2025 | about $196,000 |
| Graves Crossing Phase 2, Section 2 | $29,894 | June 2, 2025 | about $299,000 |
| Providence Phase 1, Section 1 | $39,253 | September 17, 2025 | about $393,000 |
The implied costs are estimates. They assume each bond matches the 10% figure the regulations call for, based on the construction costs in each phase's Standard Subdivision Contract. Even so, the scale is useful. The bond on a section is tens of thousands of dollars, sized to cover defects in workmanship. It isn't meant to pay for repaving a section later.
Both requests come more than a year after the bonds were set. Releasing them would end the developer's financial guarantee on those sections' streets and drainage. The meeting where that happens is public, and the agenda includes time for citizen comments.
The Crosswynd 2B approval came with conditions that had nothing to do with pavement. Medina's Building Inspector flagged three items:
The staff planner recommended settling those concerns before approval. The commission approved the plat on the condition that all three were met. Water for that subdivision comes from the Gibson County Municipal Water District, which draws groundwater from the Memphis Sand Aquifer according to its 2024 water quality report.
Hydrant flow measures whether the water system can support firefighting. Water pressure at the kitchen tap is a different test. Insurers may care about the difference. ISO's split classification rates properties within five road miles of a fire station and within 1,000 feet of a creditable water supply differently from those farther than 1,000 feet away. Properties more than five road miles from a station generally get Class 10. Medina's current classification wasn't in the public record we reviewed. Before closing, get an insurance quote tied to the specific address and ask the agent which classification applies.
The house and the subdivision's improvements are covered by different guarantees, so check each one separately.
Does a recorded final plat mean the street is finished? No. Crosswynd Section 2B's final plat was approved with a performance bond because the street extension and its drainage were still covered by that bond. Under Medina's regulations, a performance bond stands in for improvements that aren't finished yet.
Does the 12-month maintenance period start at my closing? No. The regulations count it from the date the governing authority accepts the subdivision improvements. Your closing date doesn't affect it.
Do Clark Family Homes or KOKA Development work in more than one subdivision? Clark Family Homes shows homes in both Graves Crossing North and Providence. KOKA Development appears in the city's records as the developer submitting plats and bond requests for Graves Crossing, Graves Crossing North and Providence.
If you're looking at a new build in Crosswynd, Steeplechase, Graves Crossing or Providence, Madaline Hudson can help you find out which phase your lot is in, where its bond stands and what to ask the City Engineer before you sign. Let's Connect.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.